Works progressing well on a replacement dwelling in Stockbridge / by Colin Tomsett

Works are progressing well on a 264m2 replacement dwelling in the center of Stockbridge within the designated Conservation area.

Demolition works commenced in mid November 2015 to clear the site followed be piling operations which consisted of 39 No piles 11m long executed by Able Piling.

Works on the superstructure commenced in January and despite the inclement weather the roof structure is nearing completion ready for covering with clay plain tiles.